Virginia 2026 Regular Session

Virginia Senate Bill SB827

Introduced
1/23/26  
Refer
1/23/26  
Report Pass
2/9/26  
Engrossed
2/12/26  
Refer
2/24/26  
Report Pass
3/3/26  
Engrossed
3/6/26  
Engrossed
3/14/26  
Engrossed
3/14/26  
Enrolled
3/30/26  
Chaptered
4/13/26  

Caption

An Act to amend and reenact ยงยง 56-585.1:5 and 58.1-3814 of the Code of Virginia, relating to pilot program for underground transmission lines; qualifying projects; levy; report.

Impact

The introduction of SB827 is expected to have significant implications on state laws governing public utilities and infrastructure management. By permitting certain transmission lines to be constructed underground, the bill seeks to streamline approval processes and encourage localities to support such projects. It allows local governments the option to impose additional levies on utility customers to cover local funding obligations for these qualifying projects, thus introducing a new mechanism for community involvement and financial responsibility in utility management.

Summary

SB827 establishes a pilot program in Virginia for underground electric transmission lines, aimed at enhancing grid reliability and promoting economic development. This bill allows public utilities to construct new electrical transmission lines of varying capacities with the provision for a portion to be placed underground if they are near residential areas. The intent is to better assess the costs, environmental impacts, and operational benefits of undergrounding these lines, which has been a topic of interest given the increasing focus on infrastructure safety and resilience.

Sentiment

The sentiment surrounding SB827 appears to be generally supportive, particularly among stakeholders interested in improving grid resiliency and modernization. However, there are concerns about the financial burdens that could be placed on localities and utility customers due to additional levies. Proponents argue that undergrounding will mitigate some infrastructure risks, while opponents may caution against the economic implications for consumers, particularly if costs are passed down through increased utility rates.

Contention

Notable points of contention within the discussions surrounding SB827 include the balance between state regulations and local autonomy regarding utility management and construction approvals. There are also discussions about affordability for consumers under the new levies and the necessity of undergrounding versus traditional overhead lines. Critics question whether the desired benefits justify the potential costs to local governments and utility customers, raising debates about the most effective approach to enhancing Virginia's electric grid.

Companion Bills

No companion bills found.

Previously Filed As

VA SB708

Underground transmission lines; qualifying projects, pilot program.

VA SB1358

Underground transmission lines; qualifying projects.

VA HB2755

Underground transmission lines; qualifying projects.

VA HB1822

Electric utilities; construction of certain electrical transmission lines, advanced conductors.

VA HB2386

Public utilities; certificate of convenience and necessity for certain new transmission lines.

VA HB2470

Electric utilities; construction of certain transmission lines, notice required.

VA SB1049

Electric utilities; approval required for construction of certain electrical transmission lines.

VA SB1022

State Corporation Commission; time frame for completion of certain transmission lines proceedings.

VA HB2003

Electric utilities; regional transmission entities; annual report.

VA HB109

Electric utilities; regional transmission entities, annual report.

Similar Bills

VA HB2755

Underground transmission lines; qualifying projects.

VA SB708

Underground transmission lines; qualifying projects, pilot program.

VA SB1358

Underground transmission lines; qualifying projects.

VA HB1487

Underground transmission lines; pilot program, clarifies qualifying projects, report.

VA SB651

Underground electric distribution & transmission improvement; levy on utility customers by ordinance.

RI H5687

Allows for measures to advance the undergrounding of certain utility cables and to have the same funded through utility rate increases to the cities of Providence and East Providence.

RI S0981

Allows for measures to advance the undergrounding of certain utility cables and to have the same funded through utility rate increases to the cities of Providence and East Providence.