Oregon 2026 Regular Session

Oregon House Bill HB4010

Introduced
2/2/26  
Refer
2/2/26  

Caption

Requires contracting agencies that procure public improvement contracts or contracts for public works and require additional work outside the scope set forth in the public improvement contract or contract for public works to issue change orders for the additional work within a specific time or to pay interest for failing to do so.

Summary

HB 4010 would require prompt written change orders and interest payments when additional work is ordered outside the original scope of a construction contract. For public improvement and public works contracts, a contracting agency that directs extra work must issue a change order within 30 days after the request and acceptance of the work, or it becomes liable for interest on the unpaid amount until the change order is issued. The bill also requires interest to be paid automatically on overdue public contract payments, and it preserves existing prompt-payment and retainage rules. The bill extends similar change-order and prompt-payment protections into private construction contracting. Under the measure, an owner that orders extra work outside the scope of a construction contract must issue a change order within 30 days, and contractors must pass that obligation down to subcontractors within 10 days after receiving the owner’s change order. If a contractor or owner fails to do so, interest accrues on the unpaid amount. The bill also requires contractors to pay subcontractors and material suppliers within seven days after receiving payment, subject to existing withholding and retainage exceptions, and awards costs and attorney fees to the prevailing party in actions to collect interest.

Impact

HB 4010 would amend ORS 279C.570 and ORS 701.630, expanding Oregon’s prompt-payment framework for construction work. It adds a specific statutory duty for public agencies and private owners to issue change orders for accepted extra work within a set time, and it creates interest penalties for delay. The bill also clarifies timing, notice, and fee-shifting rules, and it applies prospectively to covered public procurements and construction contracts entered into after the operative/effective dates. The public-contract provisions are scheduled to become operative on January 1, 2027.

Sentiment

The available record suggests the bill was generally aimed at improving payment certainty and fairness in construction contracting, especially for contractors and subcontractors performing extra work beyond the original scope. Because there are no committee transcripts or recorded votes in the provided material, there is no direct evidence of formal support or opposition in the discussion record. The bill’s structure, however, indicates a pro-contractor, pro-subcontractor policy approach focused on timely compensation and discouraging agencies or owners from delaying change-order processing.

Contention

The main points of potential contention are the new deadlines and financial penalties imposed on contracting agencies, owners, and contractors. Public agencies may object to the mandatory 30-day change-order timeline and automatic interest liability, while contractors may be concerned about being required to flow change orders and interest obligations down to subcontractors quickly. Another possible issue is how disputes over whether work was truly outside the original scope, or whether the work was “accepted,” would be resolved, since those determinations trigger the payment and interest rules. The bill also preserves exceptions for disputed work, retainage, and contract-based withholding, which may limit conflict but could still generate disputes over application.

Companion Bills

No companion bills found.

Similar Bills

No similar bills found.