New Jersey 2024-2025 Regular Session

New Jersey Senate Bill SR133

Introduced
5/22/25  
Refer
5/22/25  
Report Pass
6/12/25  

Caption

Respectfully urges Federal Energy Regulatory Commission to reject results of PJM Interconnection, L.L.C.'s 2025/2026 Base Residual Auction and require rebid.

Impact

The implications of SR133 are substantial for New Jersey residents, as the drastic increase in the auction's resource clearing price is projected to escalate the average monthly electric bill by approximately 17 to 20 percent starting from June 2025. Given that most New Jersey ratepayers are served through the Basic Generation Service auction, this situation could lead to increased financial strain on households and businesses alike, impacting statewide energy affordability and accessibility.

Summary

Senate Resolution No. 133, introduced in New Jersey, urges the Federal Energy Regulatory Commission (FERC) to reject the results of the PJM Interconnection, L.L.C. 2025/2026 Base Residual Auction (BRA) and to require a rebid. This resolution arises in light of significant concerns following the July 2024 BRA, where resource clearing prices spiked to nearly ten times higher than the previous auction, resulting in alarming forecasts of rising electricity costs for consumers in New Jersey.

Conclusion

In summary, SR133 serves as a legislative response to acute economic pressures posed by rising energy costs tied to recent auction results. By urging federal oversight and rebid of the capacity auction, the resolution strives to ensure market integrity and consumer protection, highlighting the need for regulatory frameworks that adequately reflect operational realities and fair pricing in the electricity sector.

Contention

Key points of contention surrounding SR133 include accusations of market manipulation and flaws within the PJM capacity market construct. The Organization of PJM States, Inc. and the Independent Market Monitor for PJM have raised concerns that the auction's outcomes may not accurately reflect supply and demand fundamentals. These issues, along with potential artificial scarcity of supply, underpin the urgency of the resolution, as it seeks to protect New Jersey consumers from unjustified cost increases related to electricity.

Companion Bills

NJ AR186

Same As Honors life of Congressman William J. Pascrell, Jr.

Previously Filed As

NJ SR18

Urges states in PJM Interconnection region to require data centers to obtain electricity from new zero- or low-emission sources of energy.

NJ HCR94

Urging Pjm Interconnection To Maintain Price Collars At The Current Rate And Encouraging Reforms To The Interconnection Queue.

NJ A3967

Requires BPU to work with neighboring states to research and recommend certain action concerning electric capacity and transmission.

NJ S746

Requires BPU to work with neighboring states to research and recommend certain action concerning electric capacity and transmission.

NJ A1170

Requires submission of energy usage plan to BPU for proposed artificial intelligence data centers; requires all electricity for artificial intelligence data centers to be derived from new clean energy sources.

NJ SR188

Directing the Joint State Government Commission to study the costs and benefits of continued membership in the PJM Interconnection.

NJ S680

Requires energy usage plan for proposed artificial intelligence data centers and cryptocurrency mining facilities; requires all electricity for artificial intelligence data centers and cryptocurrency mining facilities to be derived from new clean energy sources.

NJ HR361

Directing the Joint State Government Commission to study the costs and benefits of continued membership in the PJM Interconnection.

NJ SR81

Respectfully urges President Trump to promptly restore federal funding to Gateway Tunnel Project.

NJ AR39

Respectfully urges Office of Attorney Ethics to examine and audit actions of legal aid organizations.

Similar Bills