District Of Columbia 2025-2026 Regular Session

District Of Columbia Council Bill B260513

Introduced
11/24/25  
Enrolled
12/12/25  

Caption

Modification Nos. M0011 and M0012 to Contract No. CW100388 with Friendship Place Approval and Payment Authorization Emergency Act of 2025

Summary

This emergency act approves two contract modifications, M0011 and M0012, to Contract No. CW100388 with Friendship Place, a District contractor, and authorizes the District to pay up to $1,865,355.10 for goods and services already received and still to be received under the contract. The measure is framed as a procurement approval and payment authorization rather than a policy change, and it is limited in duration as an emergency act. The bill also adopts the Chief Financial Officer’s fiscal impact statement and states that it takes effect upon mayoral approval or Council override of a veto. Because it is an emergency measure, it remains in force for no longer than 90 days. The practical effect is to allow the District to continue or settle payment obligations tied to the Friendship Place contract while bypassing the ordinary procurement approval timeline. The bill’s impact on District law is narrow but direct: it creates a specific statutory authorization for these contract modifications notwithstanding the Procurement Practices Reform Act of 2010. It overrides the usual requirement for prior approval under D.C. procurement law for this particular contract action and permits payment for services under the stated cap. The affected parties are the District government and Friendship Place, the contractor receiving payment authorization. The general sentiment appears strongly supportive and noncontroversial. The recorded final reading vote was unanimous, 13-0, indicating broad Council agreement. No committee transcript was provided, and the bill’s text suggests a routine administrative approval needed to ensure continuity of contracted services and payment authority. The main point of contention, to the extent one exists, is the Council’s use of emergency authority to approve contract modifications outside the normal procurement process. However, there is no evidence in the available record of opposition to this specific measure, and the unanimous vote suggests any concerns about procurement procedure or spending were not politically divisive in this case.

Impact

The act temporarily amends the District’s procurement framework for one contract by authorizing payment and approval of specified modifications to Contract No. CW100388 with Friendship Place, notwithstanding the Procurement Practices Reform Act of 2010. It does not broadly change procurement law, but it creates a one-time statutory exception allowing the District to pay up to $1,865,355.10 for services under the contract and to recognize the contract modifications as approved for legal and fiscal purposes.

Sentiment

The available voting history indicates clear support for the bill, with a 13-0 final reading vote. No committee discussion was provided, but the unanimous vote and the bill’s administrative nature suggest the measure was viewed as a routine, necessary authorization to maintain contract operations and payment continuity rather than as a controversial policy proposal.

Contention

The only notable potential issue is procedural: the bill uses emergency authority to approve contract modifications and authorize payment outside the ordinary procurement approval process. That can raise general concerns about oversight, transparency, and bypassing standard review requirements. In the record provided, however, no member or stakeholder is identified as opposing the measure, and the unanimous vote suggests those concerns did not become a point of active contention.

Companion Bills

No companion bills found.

Similar Bills